Burnside Village Stage 6

The Stage 6 development will be the construction of approximately 18,500m² of additional floor space and 2 basement car park levels.

SCOPE: 1203 no. 600mm, 750mm and 900mm dia CFA piles up to 19m deep for Soldier Pile Retaining Wall
110 no. Temp Anchors 15m – 20m long
9 no. 600mm and 900mm dia CFA piles up to 17m deep for the foundation pile
EQUIPMENT:

Bauer BG28
Track Mounted Concrete Pump
Soilmec SM14 (anchors)

CLIENT:  McMahon Services